Can the customer use one shift of machine data?
At the acceptance test for a filling line, agree on one shift and one measured value, such as fill pressure. Give the customer the export and field definitions. Ask them to find a known interruption, explain the time zone and distinguish a missing reading from zero. Keep the sample and their result with the machine record.
The EU Data Act has generally applied since 12 September 2025. Article 3(1) applies to connected products and related services placed on the market after 12 September 2026. Determine which data and metadata fall within scope for the delivered product. A successful CSV import demonstrates that the sample is usable. It covers only the fields and access method tested. Data Act, Articles 3 and 50
What belongs in the handover file?
Consider a filling line whose pressure export contains three records. At 14:00 the reading is 2.4 bar. At 14:01 the value is empty and marked unavailable. At 14:02 the value is 0.0 bar with a valid quality flag. These are illustrative records. Ask the customer to import all three and explain the difference between the last two. If their spreadsheet turns the empty cell into zero, agree how the export or import will preserve that distinction.
File the working example with the machine serial number, the signal definition, the unit, the time zone and the export procedure. Have a customer representative repeat it with their own authorized account. Record who holds the result and who will revise the definition if a sensor changes. This exercise gives a buyer evidence for one data path. The scope of the legal obligation still depends on the product, the data and the parties involved.
Use two sign-offs. The production lead can accept that the shift file is usable. The service lead can accept that the installed release and support contact are traceable. If the pressure export passes but service cannot identify the installed version, keep the first result and leave the second item open with an owner and a retest date. That distinction matters when a machine changes hands several years later.
Can service identify the affected release?
Give the service lead a mock component notice and the machine serial number. Ask for the installed HMI application version, the published screen revision, the component record and the customer contact. Record who assesses the notice, who approves an update and how the site will confirm which version is running afterwards.
Under Article 14 of the Cyber Resilience Act, manufacturers’ reporting duties for actively exploited vulnerabilities and severe incidents affecting product security began on 11 September 2026. The main CRA requirements apply from 11 December 2027. Name the person who assesses whether a report is due and their backup before the next delivery. European Commission reporting guidance
Which 2027 date belongs in the service contract?
From 12 January 2027, providers of covered data processing services may no longer impose switching charges. Check whether the service in the contract is in scope. From 12 September 2027 the Data Act’s unfair B2B terms rules also reach certain contracts concluded on or before 12 September 2025 that run indefinitely or expire on or after 11 January 2034. Review the term of the actual contract alongside the product handover. Data Act, Articles 29 and 50